Edwards Lifesciences
Heart Valve Therapy Room Renovation
Irvine, California
Pharmaceuticals & Life Sciences
Provided & Installed:
- 15+ lighting and power distribution panels
- New 75kva UPS with 3 phase, 120/208v
Installed:
- New load-monitored Starline busway system (900 feet)
- New lighting per Title 24
Integrated:
- New 2000A ATS into existing gear and provided underground trenched connection to generator
Caltech
Design-and-Build Laser Research Laboratory Build-out
Pasadena, California
Tenant Improvement
- Demo’d existing electrical gear
- Installed new distribution
- Installed Starline busway
- Performed 3 shutdowns
- Provided wire mold for 400 receptacles
- Redesigned and reworked electrical room
- Fed power to new mechanical equipment
- Installed Title 24 lighting, controls and inverter
- Collaborated with architect, interior designer, MEP installation and engineering in an IPD project model
Six Flags
Twisted Colossus Roller Coaster
Valencia, California
General Manufacturing
Provided & Installed
- 35,000 feet of wire and specialty cables
Installed:
- All electrical, controls and sensor wiring
- 800A (480v) main electrical feed
- 8 operator stations
- 30 electrical and pneumatic panels
- programmed multiple electrical, control and pneumatic panels, sensors, sound, lighting and start-up assistance
Provided:
- Main power, wiring of motors, and installation of main MCC and VFDs
Amgen
B18S Bioreactor Panel Upgrades
Thousand Oaks, California
Pharmaceuticals and Life Sciences
- Installed complex LOTO-UPS circuit
- Established conduit layout
- Refurbished and enhanced 10 panels
- Created and submitted all drawings
- Purchased and installed mass flow meters
- Revised and enhanced WAGO/IO structure
- Provided and installed peristaltic pumps
- Modified door to accommodate controls, pumps and bulkhead fittings
- Collaborated with Emerson Delta V team in testing and startup
- Performed 15 more upgrades in a subsequent project
Johnson & Johnson/Neutrogena
Bulk WIP Upgrades and TI
Los Angeles, California
General Manufacturing
- Provided lighting and controls
- Provided power to connections and fixtures
- Provided complete engineering and installation of seismic bracing for all electrical systems
- Provided routing of conduits with new 1600A circuit breaker into existing electrical equipment
- Coordinated electrical power requirements for owner-furbished air handlers
- Integrated new architectural and steel elements, as well as hot water piping, into existing condition
- Provided layout for coordinating locations and sizes of all required frame openings with respective trades prior to construction
- Followed up with safety and training
- Ordered and installed all materials
Johnsons & Johnson/Neutrogena
Air Compressor
Los Angeles, California
General Manufacturing
Provided & Installed:
- Conduit and wire for 1600A panel board with (2) 400A breakers, (2) 125A breakers, (2) 70A breakers, (2) 20A breakers
- New (2) 2½"GRS conduit, (3) #250mcm, and (1) #4awg wires, breaker, and 400A disconnect for new 400A compressor to be fed from new panel board
- New 1½" GRS conduit, (4) #1/0, and (1) #4awg wires, breaker, and 200A disconnect for existing 125A compressor to be fed from new panel board (to be migrated in the future)
- New 1¼" GRS conduit, (3) #4awg, and (1) #8awg wires, breaker, and 100A disconnect for 70A dryer to be fed from new panel board
- New conduit, wire, breakers, and (2) 30A disconnects for 2 new condensate pumps to be fed from new panel board
Installed:
- Conduit and wire for 1600A switchboard from main gear SWG to new panel board; executed necessary trenching
Disconnection & Demo:
- Existing conduits, panels, and wire of 3 existing compressors
Johnson & Johnson/Neutrogena
North Yard Storage Canopy Build
Los Angeles, California
General Manufacturing
- Furnished and installed new 70A 480v 3-pole breaker inside existing panel from main power feed to canopy area
- Furnished and installed new 1½" GRS conduit with (4) #1awg wires and (1) #6 ground wire in same area
- Power distribution
- Furnished and installed new 125A, 480v 3-phase 4-wire panel board, new 45kVa reduced voltage transformer, and new 125A, 120/280v 3-phase 4-wire panel board
- Provided all interconnecting wires and conduit per each piece of equipment
- Furnished and installed all new furnished panel boards including branch breakers for devices and lighting systems
- Furnished and installed (3) 30A 480v, (1) 20A 208v, and (3) 20A 120v receptacles
- Provided branch wiring to all devices
- Provided 120v dedicated circuit for new local fire alarm panel
- Lighting distribution
- Provided 30 new LED fixtures rated for damp location to meet 25- to 40-foot candle levels
- Provided occupancy sensors and lighting controls as per Title 24
- Provided lighting branch wiring and junction boxes
- Provided electrical drawings as part of engineering and design, complying with Title 24 energy savings requirements
Toyota
Installation for Building J
Long Beach, California
General Manufacturing
Provided:
- Provided complete installation for 9 welders, including 480v and 120v power drops
- Provided drawings and City of Long Beach permit
Installed:
- Installed new 1½" conduits and #2awg + GND wires for 7 new welders
- Installed ¾" conduits and wires for (9) 120v receptacles
- Installed 7 new circuit breakers, 200A, 2 pole Cutler Hammer HFD2200, refurbished with 3 double buss hardware kits
Relocated:
- Conduits, wires and disconnects for 2 existing welders
AUTO Parkit
Automated Park Monitoring System
Beverly Hills, California
General Manufacturing
- Managed all panel design, panel fabrication, programming and installation
- Buried proximity sensors at every location and wired into kiosk stand to be monitored 24/7
- Completed all programming for PLC/HMI/key fob controller/reader, PC w/2 cameras
- Commissioned entire system
- Provided system training and support
VegFresh Farms
Generator Installation
Corona, California
Cold Storage
Provided & Installed:
- New 2000A ATS; matched new ATS bussing configuration for line and load loss; made all buss connections; and torqued all terminations to manufacturer’s specifications
- Temporary power flexible cable between existing utility main disconnect and distribution sections, which contain all facility loads
- New deep-junction box on building exterior containing all conductors from ATS to new generator junction box
- (5) 4" Rigid Ocal conduit stub-downs w/Ocal 90-degree elbows from exterior junction box to first 10 feet of underground conduit. After first 10 feet of conduit, transitioned from Ocal to PVC Sch-40. Each conduit contained (4) 600Lcmil conductors and (1) 350 Kcmil ground
- 3/0 bare copper grounding grid with two ground inspection wells along perimeter of rebar-reinforced structure to provide Ufer-grounding grid for new generator
- 5 new 4" Ocal stub-ups from underground trench to new generator connection point; pulled all wires and did all terminations
- New 1" conduit from generator control cabinet to new ATS inside electrical room for automatic power transfer (conduit contains 12 #14 wires for signals.)
- 1500kvw, 3-phase 277/480v w/24-hour fuel tank emergency standby generator
Additional:
- Dug trench from new exterior junction box to new generator connection point (will contain underground conduits encased in slurry)
- Coordinated shutdowns with utility company and planner
Shire
WFI Automation
Los Angeles, California
Pharmaceuticals and Life Sciences
Objectives:
1. Reduce likelihood of bioburden.
2. Change mechanical design, new location of elements.
3. Add zero-static valves, control system to support new design, and automatic valves and instrumentation.
- Installed all electrical, controls and sensor wiring
- Provided and installed 35,000 feet of wire and specialty cables
- Provided main power, wiring of motors, and installation of main MCC and VFDs
- Installed 800A (480v) main electrical feed
- Installed 8 operator stations
- Installed 30 electrical and pneumatic panels
- Installed and programmed multiple electrical, control and pneumatic panels, sensors, sound, lighting and start-up assistance
Shire
WWNS Baker Tank Controls PLC Integration
Los Angeles, California
Pharmaceuticals and Life Sciences
- Produced engineering and drawings for WWNS PLC and Baker tank control panel
- Installed new 1" PVC-coated conduit from PLC to new Baker tank control panel
- Installed 6 digital inputs wiring to PLC for an existing 7.5HP motor control
- Installed 5 interposing relays wiring to PLC for existing level float switches and 7.5HP motor controller
- Fabricated control panel with local/remote switch and all interposing relays and interconnecting wiring
- Installed analog cable for Baker tank ultrasonic level sensor using existing underground conduit. Will convert existing discrete 120V AC float switch to 24V DC.
- Provided and installed 3 Warrick control intrinsically safe barrier relays for Baker tank pump controller float switches
- Terminated all wires, checked I/O, and assisted with startup
- Installed 4" x 1.2" reducing adapter and ultrasonic level transmitter on top of existing Baker tank
- Provided and installed new current transducer as DI signal to PLC
C.H. Robinson
Refrigerated Cooler Modification
Los Angeles, California
Cold Storage
Furnished & Installed:
- New 800A 480V 3-phase 3W fully rated distribution panel fed overhead from existing 1200A main switchgear
- New 225A and 200A, 480/277V 3-phase 4W fully rated surface-mount panels to replace existing panel
- New 45KvA transformer type NEMA 480/208/120V
- New 100A 480/277V 3-phase 4W fully rated lighting surface-mount panel to feed new lighting in coolers, docks, offices and truckers’ areas
- 97 new LED cold storage lighting fixtures in several cooler areas, all surface-mounted to ceiling panels
- Occupancy sensors and lighting controls to comply with Title 24
- Power wiring for roof-mounted condenser unit refrigeration system and (3) 200A, (2) 100A and (1) 400A non-fused disconnects for condensing unit
- 480V connection and wiring for each evaporator unit, each with 2 non-fused disconnects (one for fan motor and one for electric defrost)
- Refrigeration control wiring from condenser unit to air unit, providing overload protection for each air unit
- 120V control circuits for evaporator solenoid valve groups
- Power for new MAU unit located on roof, and installed control unit outside of repack cooler
- 120V control circuits for evaporator solenoid valve groups
- (2) 480V and (2) 208V 3-phase 20A receptacles for future equipment in cooler repack room
- 120V control circuits for evaporator solenoid valve groups
- 10 double duplex 120V receptacles throughout new cooler rooms
Provided:
- 480V power and disconnect to 6 cold storage doors
- New 120V power to 15 dock levelers
- Engineering services to create complete set of drawings, and obtained city-approved permits
Relocated:
- 56 existing warehouse lighting fixtures from new cold room area to new dry storage warehouse area
Preferred Freezer Services
Big Bear (design/build project; new distribution system for new freezer warehouse)
Los Angeles, California
Cold Storage
Furnished & Installed
- approximately 1,500 light fixtures and lighting control system per CA Title 24 requirements
Installed
- (2) 4000A service for 500,000-square-foot freezer
- 2.5MW standby generator
- (4) 600HP ammonia compressors
- 4 lighting panels with emergency backup
- 31 dock levelers
- 30+ electrical panels
- 40+ forklift chargers
- 8 electric vehicle charging stations
Coordinated
- Shutdowns with utility company and planner